Business zone Tečina is located right next to the highway Zagreb – Lipovac , with settlement Babina Greda located north-east of the zone

Business zone Tečina has an area of ​​174.000m2 , consists of one particle in itself and builds a cogeneration plant and facilities suitable heat consumption for the purpose of utilization of thermal energy

Cogeneration plant and facilities are;

1. BIOMASS POWER PLANT

2. BIOMASS STORAGE

3. COLD STORAGE

4. GREENHOUSE

5. POWER PLANT ENTRANCE

6. GREENHOUSE ENTRANCE

The works started in mid- 11th (a November) month in 2014 and is planned to end or duration of the works 19 months.

During the execution of works according to schedule, the expected number of employees who perform work on the construction of the plant reaches up to 150 employees.

The investor of the building is UNI VIRIDAS d.o.o.Zagreb

Company SOKOL Ltd. Vinkovci is first started building a plant in accordance with the type of work will be present until the very end.

Recap of work performed by the firm SOKOL Ltd Vinkovci is as follows;

  • Preliminary work at the very introduction in business and organizations        container settlements which are located all participants construction
  • Earthwork covering all types of excavation , filling , compaction and landscaping at the very end of construction
  • Reinforcement and carpentry work in the preparation of monolithic buildings and terraces . (Scales , pouring buildings , foundations , reinforced concrete, windows )
  • The sewerage system of the entire plant and all useful area with the installation of the mounting separator .
  • Water supply and hydrant network
  • All types of electrical works of power from 35kV water until complete dissolution on site and facilities
  • Sophisticated concrete work with special concrete
  • Preparation and construction of roads for heavy traffic of the landscaped walking paths and all necessary equipment .
  • Construction of hot water pipeline route .

Recap of work performed by the firm SOKOL doo Vinkovci is as follows;

  • Preliminary work at the very introduction in business and organizations Container settlements which are located all participants construction
  • Earthwork covering all types of excavation , filling , compaction and landscaping at the very end of construction
  • Reinforcement and carpentry work in the preparation of monolithic buildings and terraces . (Scales , pouring buildings , foundations , reinforced concrete slab , windows )
  • The sewerage system of the entire plant and all useful area with the installation of the mounting separator .
  • Water supply and hydrant network
  • All types of electrical works of power from 35kV water until complete dissolution on site and facilities
  • Sophisticated concrete work with special concrete
  • Preparation and construction of roads for heavy traffic of the landscaped walking paths and all necessary equipment .
  • Construction of hot water pipeline route .
Hrvatske Vode
Ericsson
Hrvatski telekom
HEP
Janaf
Gabocom